| Multan Telecom Region (MTR) consists of the following districts:
1. Bahawalnagar
2. Bahawalpur
3. D.G. Khan
4. Khanewal
5. Leyyah
6. Lodhran
7. Multan
8. Muzaffargarh
9. Rahim yar khan
10. Rajan pur
11. Vehari
MTR, as a whole, has a total area of about 100,000 Sq Kms, a total population (rural + urban) of around 24 M (i.e. 14% of Total Population of Pakistan) and a population density of 240 Persons/SqKms. This project targets an urban population of 4.4M in 38 Cities/Towns of MTR (excluding the city of Multan).
Apart from providing broadband services, the project includes establishment of Educational Broadband Centres in 388 high-schools and colleges and 104 Community Broadband Centres in MTR.
Narrow band (dial-up) Internet services are available through multiple operators in all the districts, either through Narrowband Pops or Virtual Pops, via fixed line dialup as well as narrowband wireless technologies.
| |
|
Region ID:
|
Broadband MTR-1/2009
|
|
Advertised On:
|
2nd March 2009
|
|
Bidders Registered:
|
- Multinet Pakistan Pvt. Ltd.
- Pakistan Telecommunication Company Limited (PTCL)
- Wateen Telecom Pvt. Ltd.
- Wi-Tribe Pakistan Ltd.
- Worldcall Telecom Ltd
|
|
Opening of Qualification & Services Proposals:
|
Following three registered bidders submitted their Qualification & Services Proposals on 4th May 2009;
- Pakistan Telecommunication Company Limited (PTCL)
- Wateen Telecom Pvt. Ltd.
- Worldcall Telecom Ltd.
|
|
Financial Bid Opening of Technically Qualified Bidders
|
Following bidders were declared Technically Qualified and their Financial Bids were opened on 18th May 2009. Subsidy requested by each bidder, based on 100% target, is as follows;
|
|
|
Proposed Subsidy (PKR) per District |
|
S/No
|
Districts
|
PTCL
|
Wateen
|
Worldcall
|
|
1
|
Bahawalnagar
|
284,200,000
|
468,441,000
|
313,687,000
|
|
2
|
Bahawalpur
|
494,600,000
|
501,448,000
|
728,782,000
|
|
3
|
D.G.Khan
|
155,800,000
|
197,666,000
|
147,140,500
|
|
4
|
Khanewal
|
262,500,000
|
441,429,500
|
288,431,000
|
|
5
|
Leyyah
|
101,200,000
|
142,712,000
|
92,755,000
|
|
6
|
Lodhran
|
160,000,000
|
224,754,500
|
139,519,000
|
|
7
|
Multan
|
53,500,000
|
106,152,000
|
46,854,000
|
|
8
|
Muzaffargarh
|
264,500,000
|
427,026,000
|
301,130,500
|
|
9
|
RahimYarKhan
|
386,200,000
|
373,868,000
|
493,241,500
|
|
10
|
Rajanpur
|
123,100,000
|
174,893,000
|
107,969,500
|
|
11
|
Vehari
|
247,075,000
|
395,871,500
|
246,197,000
|
|
|
|
| |
Note: Lowest Bids are presented in bold: |
|
|
|
|
|
|
|
|
|
|
|
Result
|
After the process of matching lowest subsidy and selection of targets (as per USF Broadband Bidding documents – RFA clauses 47, 48, 50 and 51), the contracts that have been signed with the two bidders are summarized below.
| Bidder |
Presence |
Target No. of Broadband Connections |
Target No. of EBCs |
Target No. of CBCs |
Subsidy Amount (PKR) |
Contract Signed on |
| PTCL |
All 11 Districts |
63,000 |
206 |
58 |
1,161,044,000 |
25th June 2009 |
| Worldcall |
9 Districts (Excluding Bahawalnagar and Rahim Yar Khan) |
38,500 |
121 |
27 |
785,721,250 |
28th July 2009 |
|
| |
EBC=Educational Broadband Center
CBC=Community Broadband Center |
| |
Note: LOI was sent to Wateen Telecom Pvt. Ltd. however Wateen surrendered Rahimyar Khan and Bahawalpur districts hence their bid bond was forfeited. |
| |
Region Name
|
Operator
|
Broadband connections provided so far
|
MTR
|
PTCL
|
16,812
|
Worldcall
|
0 |
| | Information Package can be downloaded from here.
For WinZip Format click here.
For WinRaR Format Click here
(If you don't have WinZip, please download from here)
(If you don't have WinRaR, please download from here) |
|
|